- Last updated
Background
Respond to the growth of domestic power consumption, Taiwan Power Company (TPC) follows the government’s energy policy and promotes the " Taichung Combined Cycle Power Plant Project" to ensure stable power supply. TPC plans to install two gas-fired Combined Cycle units in adjacent to the existing Taichung coal-fired Power Plant station , with a total capacity of about 2.6million kilowatts. This project also includes one berth liquefied natural gas(LNG) unloading pier, a LNG gasification terminal with five LNG storage tanks and associated auxiliary facilities and pipelines, which will be TPC’s first built and self-operated LNG terminal.
Project Location and Scope
The Taichung Combined Cycle Power Plant Project, covering an area of 13.4 hectares, is seated in the Southern of Unit 9 and Unit 10 coal-fired units of Taichung Power Plant.
New Design Units Specification
Item | Parameters |
---|---|
No. of Unit | 2 |
Single Unit Capacity | 1.3 million kilowatts each |
Unit Type | two gas-fired Combined Cycle units |
Thermal Efficiency | 64.1% (LHV, Net) |
Net Combustion | 5,616.22 kJ / kWh (LHV, Net) |
Gas turbine | indoor type, heavy duty for power generation (Heavy Duty), 3,600 rpm |
Steam Turbine | longitudinal series, condensing, 3,600 rpm |
Heat Recovery Steam Generator | indoor type, triple pressure reheating |
Generator | hydrogen or air cooled |
Transformer | outdoor oil immersion |
Project Progress
Schedule | Actual | Difference |
---|---|---|
50.16 | 49.65 | -0.51 |
Unit 1 | Unit 2 |
---|---|
2025/08/31 | 2026/08/31 |
The Project schedule amendment was officially approved by the Executive Yuan on October 5, 2022.
Construction Status:
-
Power Block:The Bid for Power Block has been awarded on 2020/9/1, the winning tender is GEII (General Electric International Inc)/CTCI consortium team. The construction has started on 2021/9/16, and soil improvement (sand compaction pile method) was completed on 2022/7/21. Foundation Work and plant structure are currently being carried out.
-
Circulating Water System:The Bid opening for Circulating Water System has been awarded on 2020/10/26. The onsite construction work started on 2021/9/1. Foundation Work in Circulating Water Pump House Area completed on 2023/8/26 . At present, the construction of structure in the fifth and sixth elevated water tunnel walls in the pump room area.
-
Selective Catalytic Reduction System (SCR) is used for environmental protection.
Pollutant Emission Concentration SOx 8 ppm NOx 5 ppm Particulate 10 mg/Nm3