Units No.5~10 Air Quality Control System (AQCS) Retrofit Work Project of Taichung Power Plant

Project Description

Background

Unit No. 5~10 of Taichung Power Plant have achieved outstanding performance since they were put into operation in 1996. However, due to the increasingly stricter standards of the central and local environmental protection regulations in recent years, the existing units will be retrofitted to supply the stable power and meet the environmental protection standards in the future operation life time by improving the air pollution control equipment, reducing various pollutants - NOx, SOx, PM, etc., for stable power supply.

Retrofit Scope

Improvement of Air Quality Control System(AQCS) includes the selective catalyst reduction (SCR .The SCR system shall be retrofitted to enhance the Mercury (Hg) oxidation rate),flue gas desulfurization equipment(FGD) , wet electrostatic precipitator(WESP) and media gas-gas heater(MGGH).

Improvement of Air Quality Control System
Improvement of Air Quality Control System

Expected Effectiveness

The plan is expected to improve the existing NOx, PM and SOx control equipment of unit 5 to 10, so that the air pollutant concentration discharged by the units can be lower than the requirements of the air pollutant emission regulation of electric power facilities of the environmental protection Bureau of Taichung City Government (implement on 2024/01/01):

  1. Nitrogen oxide (NOx):  the concentration discharged will be reduced to 20ppm.
  2. Particulate Matter (PM): the concentration discharged will be reduced to 5mg/Nm3 
  3. Sulfur oxide (SOx): the concentration discharged will be reduced to 10 ppm.

 

Progress Status

Project Progress

Overall Progress (%)(August-2024)
Schedule Actual Difference
78.46 78.46 0
 
Unit Reaches Flue Gas Introduction Date
Units Introduction Date
Unit 7 2023/03/25
Unit 8 2023/06/12
Unit 5 2024/04/07
Unit 6 2024/05/27
Unit 9 2025/04/08
Unit 10 2025/06/27

 

 

Construction Status

Unit 7 & 8 AQCS retrofit work has been completed, and Unit 5 was shut down on August 12, 2023, and reached the milestone of flue gas introduction on April 7,2024. The trial run test is completed, and related reports are reviewing. Unit 6 has been shut down since October 1, 2023, and reached the milestone of flue gas introduction on May 27, 2024. The trial run test is sustained in progress. Unit 9 has been shut down since July 13, 2024. This unit is going on demolishing and civil engineering.