Overview of Thermal Power Plants Projects

Taiwan produces very poor energy, and imported energy is as high as 98%. In addition to develop renewable energy, it is still necessary to continue to develop power supplies. Due to the low proportion of base-loaded power supplies in Taiwan, Taipower will adversely control power generation costs and reduce regional power supply and demand. In the unbalanced situation, Taipower actively promoted a number of large-scale power generation projects, including Tung Hsiao, Datan, Hsinta, and Taichung gas recirculation units, which can maintain reasonable spare capacity targets to provide sufficient power support. economic development.

 

Ongoing Thermal Power Plants Projects

 
Datan Combined Cycle Power Plant Expansion Project
Contents of Project Total investment Commercial operations date
Planning to add three gas combined cycle units, each of which has a capacity of 1 GW at the current plant site, bringing the total capacity to 2.88-3.168GW 110.46 billion Phase two of Unit 7 2025/05/01
Unit 8 2024/07/31
Unit 9 2025/03/01

 

 

Hsinta Power Plant Combined Cycle Renewal Project
Contents of Project Total investment Commercial operations date
The total Project capacity is about 3,900 Mega watts of Combined Cycle Units.
(Note 5) 
116.87 billion Unit 1 2024/02/29
Unit 2 2024/06/30
Unit 3 2025/08/31

 

 

Taichung Combined Cycle Power Plant Project
Contents of Project Total investment Commercial operations date
Planning to add two gas combined cycle units, each of which has a capacity of 1 GW at the current plant site, bringing the total capacity to 2.88-3.168GW 118.06 billion Unit 1 2025/08/31
Unit 2 2026/08/31

 

 

Location of Power Plants

Location of Thermal Power Plants